| | Job | Progress | Comments |
| Main house | Foundations | Completed | Finished September 2004 |
| Rising walls | Completed | Finished September 2004 |
| External walls | Completed | Finished October 2005 |
| Roof | Completed | Finished November 2005 |
| Loft Insulation | 99% done | Main part of loft completed, just one area over the hall needs the second 200mm laid (one rolls worth)
|
| External doors & windows | Completed | Installed July 2006, front door refitted Jan 2007. |
| Sewerage & drainage | completed | Biocycle unit installed, all sewer pipes laid |
| Rainwater system | 50% done | Gutters fitted, Downpipes fitted after plastering. Rainwater harvesting system to be installed during driveway construction.
|
| External render | completed | completed November 2007
|
| Floor slab & UFH pipes | Completed | UFH Installed June 2006, concrete poured July 2006 |
| Internal studwork | Completed | Finished September 2006 |
| Electrics | Completed | 1st fix September 2006,Lights & sockets wired spring 2007 and live 20 April, temporary electrics removed. Garage is a separate project |
| Data & TV cables | First fix | Installed September 2006, some cabling runs completed,
|
| Plumbing & heating | 98% | Installed July 2006, Heating tested Jan 2007, Rainwater harvesting system to be installed
|
| Ventillation system | Completed | Installed August 2006, commissioned late April 2007 |
| Internal joinery | Second fix almost complete | Most rooms completed, just some fitting-out behind the Television |
| Move in | Complete | 11 May 2007 |
| Garage / store shed | Foundations | Complete | November 2005, foundations re-dug, concrete poured 1st week December, rising walls built & hardcore laid 3rd week December. |
| Walls | Completed | Walls erected mid January, gable ends late January |
| Floor | Complete | concrete poured 30 March |
| Roof | 95% done | Roof slated and just need facias, soffits & gutters fitted. |
| Solar panels | 90% complete | Frame fitted to the roof. Panels assembled and installed in the roof, now producing decent amounts of hot water. Tank insulated and connected to main house plumbing system Another set of panels will be made during the winter to replace the current ones as there are teething troubles with them. |
| Wood Boiler & silo | Not started | Postponed for a couple of years |
| External render | Not started | Postponed for a couple of years |
| Electrics & Plumbling | 90% completed | Consumer unit fitted, wall sockets and lights installed, one double socked still to be fitted. External water tap fixed to wall, also gas pipe attached to wall. |
| External doors & windows | 95% complete | Side door, Garage door & window fitted, just need to glaze the side door |
| External works | Driveway | Sub-base completed | Temporary surface, until all other works completed |
| Enterance | Temporary farm gate in place | Start this after landscaping |
| Pathway around house | Some hardcore laid | Start this after external render |
| Front walls | Not started | Start this after landscaping |
| Hedging | Most planted | Planted first row in Dec 2005, Planted additional hedging & infill hedging Dec 2007 |
| Landscaping & land drainage | 85% done | Site was levelled and seeded in August 2007,
|
| Gardens | 30% | Basic lawns in place with some spring bulbs planted at the front |
| Patio | Some hardcore laid | Start this after external render |