Room by room progress PDF Print E-mail
Saturday, 23 December 2006 12:15

Jobs & progress.

We have now moved in but there are still many jobs to do!

To see the images full size - please go to the diary section and click on "room by room progress" and click on any of the images.

Finished Jobs in Green

Changes since previous update are in red, as of 22 September 2008

  Job Progress Comments
 Main house Foundations Completed Finished September 2004
 Rising walls Completed Finished September 2004
 External walls Completed Finished October 2005
 Roof Completed Finished November 2005
 Loft Insulation 99% doneMain part of loft completed, just one area over the hall needs the second 200mm laid (one rolls worth)
 External doors & windows Completed Installed July 2006, front door refitted Jan 2007.
 Sewerage & drainage  completed Biocycle unit installed, all sewer pipes laid
 Rainwater system50% doneGutters fitted,  Downpipes fitted after plastering.  Rainwater harvesting system to be installed during driveway construction.
 External render  completed completed November 2007
 Floor slab & UFH pipes Completed UFH Installed June 2006, concrete poured July 2006
 Internal studwork Completed Finished September 2006
 Electrics  Completed 1st fix September 2006,Lights & sockets wired spring 2007 and live 20 April, temporary electrics removed.  Garage is a separate project
 Data & TV cables First fix Installed September 2006, some cabling runs completed,
 Plumbing & heating98% Installed July 2006, Heating tested Jan 2007, Rainwater harvesting system to be installed
Ventillation system   Completed Installed August 2006, commissioned late April 2007
 Internal joinerySecond fix almost complete Most rooms completed, just some fitting-out behind the Television
 Move in Complete 11 May 2007
 Garage / store shed Foundations  Complete November 2005, foundations re-dug, concrete poured 1st week December, rising walls built & hardcore laid 3rd week December. 
 Walls Completed Walls erected mid January, gable ends late January
 Floor Complete concrete poured 30 March
 Roof 95% done Roof slated and just need facias, soffits & gutters fitted.
 Solar panels 90% complete Frame fitted to the roof. Panels assembled and installed in the roof, now producing decent amounts of hot water. Tank insulated and connected to main house plumbing system Another set of panels will be made during the winter to replace the current ones as there are teething troubles with them.
 Wood  Boiler & silo Not started Postponed for a couple of years
 External render Not started Postponed for a couple of years
 Electrics & Plumbling 90% completed

 Consumer unit fitted, wall sockets and lights installed, one double socked still to be fitted.

External water tap fixed to wall, also gas pipe attached to wall.

 External doors & windows 95% completeSide door, Garage door & window fitted, just need to glaze the side door
 External works Driveway Sub-base completed Temporary surface, until all other works completed
 Enterance Temporary farm gate in place  Start this after landscaping
 Pathway around house Some hardcore laid Start this after external render
 Front walls Not started Start this after landscaping
 HedgingMost plantedPlanted first row in Dec 2005, Planted additional hedging & infill hedging Dec 2007
 Landscaping & land drainage 85% doneSite was levelled and seeded in August 2007,
 Gardens30%Basic lawns in place with some spring bulbs planted at the front
 Patio Some hardcore laid Start this after external render

Room by room progress

 

 Room Job Progress Comments Image
 Kitchen/Diner Fix Fermacell Completed
 All work in the kitchen completed!
 Active Image
 Kitchen units Completed
 Fill & skim Completed
 Paint wall & ceiling Completed
 Tile floor Completed
Fit door & skirting Completed
 Living room Fix Fermacell CompletedRoom is now almost completed still have some work on the TV wall mounting system
 Active Image
 fill & skim Completed
 Paint wall & ceiling Completed
 Tile floor Completed
 Fit doors  & skirtingCompleted
Utility Fix FermacellCompletedAll Units fitted room finished  Active Image
 Fill & skimCompleted
 Paint wall & ceilingCompleted
 Tile floor Completed
 Fit door & skirting Completed
 Study Fix Fermacell CompletedAll buildiing work complete here.Active Image 
 Fill & skim Completed
 Paint wall & ceiling Completed
 Tile floor Completed
 Fit door  & skirting Completed
 Master Bedroom Fix Fermacell Completed  All building work completed, room cleaned  and furniture moved in, finished!! Active Image
 Fill & skim Completed
 Paint wall & ceiling completed
 Tile floor Completed
 Fit doors  & skirting Completed
 Bedroom 2,(guest & playroom) Fix Fermacell CompletedAll building work completed,  room cleaned  and furniture moved in, finished!! Active Image
 fill & skim Completed
 Paint wall & ceiling Completed
 Tile floor Complete
 Fit doors  & skirting Completed
 Bedroom 3, (Jack) Fix Fermacell CompletedAll building work completed, room cleaned  and furniture moved in, finished!! Active Image
 Fill & skim Completed
 Paint wall & ceiling Completed
 Tile floor Completed
 Fit doors  & skirting Completed
 Bedroom 4, (Molly) Fix Fermacell Completed All building work completed, room cleaned  and furniture moved in, finished!! Active Image
 fill & skim Completed
 Paint wall & ceiling Completed
 Tile floor Completed
 Fit doors  & skirting Completed
 Bathroom Fix Fermacell Completed Shower and sanitoryware have been fitted, CompleteActive Image 
 Fill & skim Completed
 Paint  ceiling Completed
 Tile floor & walls Completed
 Fit door  Completed
 En-suite Fix Fermacell Completed  Shower and sanitoryware have been fitted, CompleteActive Image 
 fill & skim Completed
 Paint  ceiling Completed
 Tile floor & walls Completed
 Fit door  completed
 Hall Fix Fermacell Completed Completed. Active Image
 Fill & skim Completed
 Paint wall & ceiling Completed
 Tile floor Completed
Fit doors  & skirting Compteted
 Toilet  Fix Fermacell Completed Completed Active Image
 fill & skim Completed
 Paint wall & ceiling Completed
 Tile floor Completed
 Fit door & skirting Completed
 Hot press Fix Fermacell Completed Heatbank & cold water accumulator connecter up, have tested UFH & immersion heaters. We now have hot water & heating - (backup) oil boiler in the garden behind the garage providing heat. Airing cupboard shelving now in place
Active Image 
 Fill & skim Completed
 Paint wall & ceiling Completed
 Tile floor Completed
 Fit door  completed

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Last Updated on Monday, 22 September 2008 14:09
 